Thompson Peak Parkway crosses Reata Wash between East Desert Camp Drive and East Windgate Pass Drive. At that point the road changes shape. Four travel lanes and two bike lanes narrow into two travel lanes and two bike lanes, with one lane each way over a single bridge. Then the road widens again on the other side.
That narrowing was planned from the start. The bridge you cross today was always meant to have a twin. As of this month, crews are building it.
A Bridge Designed in Pairs
When DC Ranch was developed, the City of Scottsdale and the developer signed an agreement covering this crossing. The developer would design two bridges over Reata Wash but build only one, because the new community did not yet have the traffic to justify both. Once the area grew and traffic warranted it, the city would build the second.
DC Ranch built the first half-street bridge in 2000, according to a city Paths & Trails Subcommittee presentation from 2025. For 26 years it has carried traffic in both directions.
The city's own project page says that bridge has kept up with car traffic. Bicycles changed the picture. As more riders use this stretch of Thompson Peak Parkway, the narrowed crossing has become a safety concern for both drivers and cyclists. So the case for finishing the pair rests on the people riding the bike lanes as much as on the cars.
How a 2019 Bond Item Reached Groundbreaking
The second bridge reached the ballot as Project 62 in Scottsdale's 2019 bond election, under Question 2, Community Spaces and Infrastructure. Voters approved all three bond questions on Nov. 5, 2019. The DC Ranch Community Council's project page says DC Ranch pushed to get the expansion done, and that it was the only transportation project in that bond.
Here is how the project moved from the ballot to the wash:
- February 2020: City staff presented the 2019 Bond Project Implementation report at a Feb. 11 council work session, listing all 58 bond projects with projected dates.
- March 13, 2020: The city manager at the time told the DC Ranch Community Council the bridge would move up to 2024, the fifth year of the bond program.
- March 2023: The city confirmed a schedule of design in 2024 and construction in 2025 to 2026. The update noted that inflation and national construction delays had raised costs across the bond program, and that no bond projects had been eliminated.
- June 2024: The council's FY24/25 budget included design funding.
- March to July 2025: Kimley-Horn, the design consultant, began the environmental and cultural resource surveys required before construction bids.
- Sept. 22, 2026: City Council approved Resolution 13778, authorizing a contract with Ames Construction, Inc. for up to $8,085,461.26 in construction services.
- Oct. 27, 2026: The city held a groundbreaking ceremony. Construction began Monday, Nov. 2.
The money grew along with the timeline. The city's 2019 bond program page lists Project 62 at $6.3 million. The full project budget is now $14.2 million. Most of it comes from the bond and the rest from the city's 0.2% transportation sales tax.
What's Happening in Reata Wash Right Now
Most of the first phase takes place below the road. The city's project page describes it like this:
| Work in the initial phase | Where it happens | Effect on travel lanes |
|---|---|---|
| Salvaging and relocating native plants | In and along the wash | Lanes stay open |
| Locating, and possibly relocating, underground utilities | Below grade | Lanes stay open |
| Drilling shafts for the bridge supports | Below grade in Reata Wash | Lanes stay open |
| Contractor staging area and temporary plant nursery | On-site | Lanes stay open |
Crews work Monday through Friday, 7 a.m. to 5 p.m. If you notice something unusual near the site, the project hotline is 602-290-0729.
The temporary plant nursery is a good sign of how this phase works. Native plants are dug up before the drilling starts and kept on-site, rather than cleared away.
The city's groundbreaking announcement quoted Alison Tymkiw, the city's senior director of transportation and infrastructure, on why the work starts in the wash:
"The second bridge will provide consistent travel lanes and dedicated space for people biking and walking across the wash. Our initial construction activities will take place largely below the roadway, allowing us to begin this important work without affecting travel lanes."
The city's commitment to open lanes covers this initial phase. Before the deck goes on, check the project page for an updated plan.
What the Finished Crossing Adds
The new structure is a two-lane bridge that mirrors the one already there. The 2025 Paths & Trails presentation lays out its cross-section:
- Two 12-foot vehicle lanes
- A five-foot bike lane
- A five-foot sidewalk
- A pedestrian barrier
Once both bridges are open, each one carries traffic in a single direction. Thompson Peak Parkway will then have four continuous travel lanes with bike lanes all the way from Scottsdale Road to 100th Street. The city also says the finished parkway improves access to nearby parks and schools.
The change people riding and walking will notice is the space around them. Today the bike lanes and sidewalk cross the wash beside one lane of traffic each way. With the second bridge, each direction gets its own two lanes, its own bike lane and its own sidewalk.
The project will also include a piece of public art, which city ordinance requires for projects like this one.
Making the New Half Match the Old
The DC Ranch Community Council reviewed the city's initial designs in July 2026, with a focus on how closely the new bridge would match the original. Its feedback to the city included these points:
- Use real stone, specifically DC Cobble, to match the original bridge, not imitation stone.
- Leave off Jersey barriers along the full length of the bridge, and consider dropping the sidewalk and continuing the natural path through the wash instead.
- Metal railings are acceptable in place of wood if their design matches the original. The original bridge's railings, which are in poor condition, should also be replaced with metal.
- Removing the arched supports under the bridge is not the council's preference, but it understands the cost savings to the city.
Residents who wanted to see the design and schedule in person had their chance on Sept. 9. The city held a public open house that evening at The Homestead. The Community Council's running project page has posted updates on the bridge since the 2019 bond election. It is the most direct place to follow how the finished design treats stone, railings, and the wash path.
Through Next Fall
The city expects construction to take about 12 months from the Nov. 2 start, which puts the new bridge at around fall 2027. The Scottsdale Independent also covered the groundbreaking and the $14.2 million project.
Until the second bridge opens, the crossing between Desert Camp Drive and Windgate Pass Drive stays what it has been since 2000: one lane each way over the wash. Crews work weekdays from 7 a.m. to 5 p.m., the hotline is 602-290-0729, and the city's project page will carry any changes to lane plans as the work rises out of the wash.
If you have questions about how the Thompson Peak Parkway work fits into your plans in DC Ranch, the team at Shields Regal Realty is glad to talk it through with you. Contact Us anytime.